Our plan is that we will place a 20 ft (half size) container near one of the dust source regions in Kangerlussuaq. Potential locations are accessible by road by to the SE or NE of the town. The SE site has power nearby but the NE site is unlikely to have power supply.

In the second case, we might need generators with a total power of 10 kwh.

The planned fieldwork will be in late Aug to Sep in 2022 and will last for a month.

We will have about a total of 12 scientists on site to support the fieldwork.